3G Pitch Installation - Progress Report Week 9

Longmead Pitch Works July 2022 Week 9

Its not just the pitch but new perimeter fencing and floodlight pylons all taking shape


Operations Director Ian Clear writes:
 

Pitch works - Week 9. The stone sub-base is being finished off this week in preparation for the "Blinding Layer" which is the final layer before the shock pad and artificial surface is installed. Floodlight pylons have been installed this week and work on the new perimeter fence continues.


Pictures : Ian Clear







 

Published Friday 1st July 2022