3G Pitch Installation Week 10 - Progress Report
New Dugouts arrive
Operations Director Ian Clear gives his latest update:-
The binding layer should be completed today (7th July), work can then start on laying the 25mm shock pad which will take about 5 days. Perimeter fencing is almost complete and the floodlight brackets have been fitted. The pitch drainage system has been connected to the main drain and the new Dugouts have arrived.
The works are a little behind schedule due to difficulty sourcing aggregate and sand for the binding layer. I'll have the revised completion date next update, but the pitch will be ready for the first home fixture on 6th August. Ian Clear